Partix Docs

Steps

Steps, also called operations, describe the work to do. Each step has its own material and completion status.

The three types

Type What it does
Pick from inventory Raises a release that issues reserved stock into the build
Purchase parts Carries material that has to be bought before this build can run
Build / process Labor only. Consumes no material of its own

The type decides what the step offers when somebody works it. A pick step shows the release controls; a process step goes straight to completion.

Add steps

Steps are added when the order is created and can be edited while it is a draft. Each takes:

A work order needs at least one step before it can be submitted.

Add steps to each order

Saved step templates are not available yet.

Assigning material to steps

Assign material to the step that uses it. This lets you record scrap where the loss happened.

A part can only be on one step.

Working a step

79-steps-panel.webpA step expanded on the work order page, showing its material and the controls to work it.

Whoever is assigned opens the step and works it:

  1. Start — marks the step in progress.
  2. Material — for a pick step, raise and issue the release. For a purchase step, record what was bought. See Pick material.
  3. Complete — close the step with a note.

Steps can be worked out of sequence. For example, you can start step 3 before step 2.

Planned dates are entered manually

Planned dates on a step are what somebody typed. Step 3's start is not derived from step 2's end, and there are no work centers or capacity limits. Dates are for expectation and for the Overdue flag, not for a schedule Partix maintains.

Attachments and print-outs

A step can carry its own documents. A pick step can also produce a printable pick list of what to pull, for shops working off paper at the shelf.