Partix Docs

The work order list

Use the Production screen to track work orders and see which ones need attention.

77-production-list.webpThe production list, with progress in three measures and one attention flag per row.

What each row shows

Column
Number and name The order's identifier and what it is building
Item What is being made, with its image
Quantity How many, and how many are done
Status Where it is in the lifecycle
Progress Three separate figures — see below
Attention One flag, when something is wrong

Track progress

Every order reports progress as steps, material and output, kept separate.

Check all three figures. An order can be nearly finished with its steps and still be short of material.

The attention flag

A row carries at most one flag — the one that most blocks the build. In order of severity:

Flag Means
On hold Paused, with the reason shown
Short Material is not fully reserved
Overdue Past its planned end date and not finished
Scrapped Units have been lost on this build

Open the order's Attention tab to see all issues.

An order with no flag is not necessarily fine

The flag catches states Partix can detect. A build that is quietly behind because nobody has touched it in a week has nothing to flag — that is what the planned dates and the Overdue flag are for.

Finding things

Filter by status, priority and assignee, or search by number and name.

The most useful filter for a production meeting is status In progress plus On hold — everything live, and nothing finished or abandoned.

Opening one

Click any row to open the full work order. See The work order page.